Schedule

The prefeasibility study was completed in the fall of 2011 and immediately followed by the feasibility study that will be completed in December 2012. Following this, construction could begin in January 2013 and end in December 2015. A one-year period is planned for the commissioning and startup of the new facilities.

 

Environment

Environmental impact
assessment

    April 2009 to December 2009

    Engineering

    Design

      June 2008 to December 2008

      Prefeasibility

        January 2009 to November 2011

        Feasibility

          November 2011 to December 2012

          Execution

          Project execution

            January 2013 to December 2015

             

             