Schedule

The prefeasibility study will be completed in December 2010. If the conclusions of the study meet Alcoa’s objectives, a feasibility study will be initiated in January 2011 to be concluded in December of the same year. Following this, construction would begin in January 2012 with completion to be slated in December 2015. A one-year period is planned for the commissioning of the new facilities.

 

Environment

Environmental impact
assessment

April 2009 to December 2009

Engineering

Conceptualization

June 2008 to December 2008

Prefeasibility

January 2009 to December 2010

Feasibility

January 2011 to December 2011

Construction

Project execution

January 2012 to December 2015

 

 