Schedule
|
The prefeasibility study was completed in the fall of 2011 and immediately followed by the feasibility study that will be completed in December 2012. Following this, construction could begin in January 2013 and end in December 2015. A one-year period is planned for the commissioning and startup of the new facilities.
Environment
|
|
Environmental impact assessment
|
April 2009 to December 2009
|
Engineering
|
|
Design
|
June 2008 to December 2008
|
|
Prefeasibility
|
January 2009 to November 2011
|
|
Feasibility
|
November 2011 to December 2012
|
Execution
|
|
Project execution
|
January 2013 to December 2015
|
|
|
|
|