Schedule
|
The prefeasibility study will be completed in December 2010. If the conclusions of the study meet Alcoa’s objectives, a feasibility study will be initiated in January 2011 to be concluded in December of the same year. Following this, construction would begin in January 2012 with completion to be slated in December 2015. A one-year period is planned for the commissioning of the new facilities.
Environment
|
|
Environmental impact assessment
|
April 2009 to December 2009
|
Engineering
|
|
Conceptualization
|
June 2008 to December 2008
|
|
Prefeasibility
|
January 2009 to December 2010
|
|
Feasibility
|
January 2011 to December 2011
|
Construction
|
|
Project execution
|
January 2012 to December 2015
|
|
|
|
|